Cat Linh - Ha Dong elevated railway to begin trial run in October
The Cat Linh–Ha Dong elevated railway will begin its test run in October before being put into official operation in the second quarter of 2018.
A rail carriage prototype for the Cat Linh-Ha Dong light railway was displayed in Hanoi in late October for public comment.
The test will take place for three to six months, according to Le Kim Thanh, director of railway projects management unit under the Ministry of Transport.
The deadline for the project has been delayed several times.
To date, about 90% of construction work has been completed, including stations, stairways connecting stations with the ground and 13 kilometres of tracks.
The elevated railway project began in 2011 with investment of US$552 million, of which US$169 million came from Chinese official development assistance. In November 2014, it was announced the project would need a total of US$868 million, US$300 million more than initial estimates.
Linking Cat Linh Street in Dong Da district with Yen Nghia station in Ha Dong district, the project includes 12 stations and a depot at Phu Luong ward in Ha Dong district.
The elevated project has a length of about 13 km, while the depot in Ha Dong spans 19.6 hectares.
Most read
Recommended
National
Viet Nam News Today (Oct. 7): Viet Nam, Panama Highlight New Opportunities for Trade and Investment
National
Vietnam News Today (Oct. 6): Viet Nam Prepares For Signing Trade Deal With European Free Trade Area
National
Vietnam News Today (Oct. 04): Vietnam Posts GDP Growth of 9.95% in Q3
National
Efforts to Bring Fallen Soldiers Home to Their Families
Popular article
National
Vietnam News Today (Oct. 3): Vietnam’s Message to The world: Peace, People And Technology For Humanity
National
Expanding Opportunities for Cooperation with Foreign NGOs
National
Vietnam News Today (Oct. 1): Viet Nam, India Move to Deepen Business, E-commerce Connectivity
National